Alicante's Local Government Board (Junta de Gobierno Local) approved the enforcement of a court order (auto) at its weekly meeting on Tuesday 10 November. The city must pay the operator of its paid blue-zone parking scheme (zona azul, known as ORA) unpaid bills totalling €1,232,937.05. The payment covers services from September to November 2025, according to Alicante Plaza.

The total breaks down into €424,081.40 for regulated parking (estacionamiento regulado), €773,533.72 for vehicle removal (arrastre) and €35,321.93 in late-payment interest. The claim was made by the joint venture (UTE) of Vectalia and Pavapark, the current operator of paid parking, vehicle removal, wheel clamping and storage at the car pound.

The court order was issued on 21 September. The court partly granted an interim measure (medida cautelar) requested by Vectalia and Pavapark. Deputy mayor Manuel Villar (PP), co-spokesperson of the ruling coalition, said the approval was needed so the council could comply with the ruling as soon as the court required it.

A week earlier, the council approved €1.9m in payments on other claims: €1.1m to SICE and Becsa for street lighting, some of whose bills dated back to 2020 and ended up in court; €599,000 to Geamur, the former contractor for maintaining green spaces; and €201,000 to Bertolín for the redevelopment of avenida de Jijona. After that payment, Villar said the council was already working on measures to prevent delays in paying bills of this kind.

Paid parking is still run by Vectalia and Pavapark under an emergency extension (prórroga extraordinaria), as all possible extensions of the previous contract have now been used up. A new 19-year contract went out to tender in April. The Central Administrative Tribunal for Contract Appeals (Tribunal Administrativo Central de Recursos Contractuales, TACRC) rejected complaints from Seteki and from Vectalia-Pavapark about the tender conditions (pliego de condiciones). On Friday 6 November, mobility councillor Carlos de Juan told a full council meeting (pleno), in reply to a PSOE question, that the claimed costs are being checked to see whether the contract's economic balance still holds.

The new contract would extend the service to a further 3,077 parking spaces, most of them in the orange zone (zona naranja), where local residents do not have to pay.

The Compromís group on the council says that repayments of subsidies, compensation and interest linked to lost grants and concession claims total more than €10.2m (€10,241,126.79), not counting the current €1.2m. Its spokesperson, Rafa Mas, says the city lost €200,000 from the regional culture department (Conselleria de Cultura) to restore the towers of the town hall building because the works contract was delayed. He also lists other sums he says were lost: a possible €1.2m in European aid for a municipal housing project on calle Ceuta, €1.2m in payments for the redevelopment of avenida de Jijona, and more than €1.5m in compensation to Geamur.

Compromís has proposed that councillors from the ruling group cover these payments by giving up their salaries, and has demanded an explanation. The article does not include a response from the ruling coalition. Mas has also given different figures in other comments, including around €15m overall and €1.3m plus €100,000 in delay charges for this payment. These do not match the council's own breakdown, and the figures have not been independently verified.